Leads and lags are evaluated and, if necessary, modified as part of which process? a. Scope development

Question:

Leads and lags are evaluated and, if necessary, modified as part of which process?

a. Scope development

b. Duration estimating

c. Analogous cost estimating

d. Schedule development