Suppose your PV for a project was $100,000 and your EV was $60,000. Your Schedule Performance Index

Question:

Suppose your PV for a project was $100,000 and your EV was $60,000. Your Schedule Performance Index (SPI) for this project would be:

a. 1.52

b. .60

c. You cannot calculate SPI with the information provided

d. 1.66