The major disadvantage of using bar charts to manage a project is that bar charts: A. Do
Question:
The major disadvantage of using bar charts to manage a project is that bar charts:
A. Do not show dependencies between activities
B. Are ineffective for projects under one year in length
C. Are ineffective for projects under $1 million in size
D. Do not identify start and end dates of a schedule