The upper and lower control limits are typically set: A. One standard deviation from the mean in
Question:
The upper and lower control limits are typically set:
A. One standard deviation from the mean in each direction.
B. 3 σ (three sigma) from the mean in each direction.
C. Outside the upper and lower specification limits.
D. To detect and flag when a process may be out of control.