Todd is working on resource scheduling in preparation for the start of a project. There is a potential problem in the works, however, as the new collective bargaining agreement with the company’s union has not been concluded.
Todd decides to continue working on the resource schedule in anticipation of a satisfactory settlement. Todd’s approach would be an example of which method for dealing with risk?
a. Accept it
b. Minimize it
c. Transfer it
d. Share it