A task has a normal duration of 9 days and crash duration (the minimum duration) of 7
Fantastic news! We've Found the answer you've been seeking!
Question:
A task has a normal duration of 9 days and crash duration (the minimum duration) of 7 days. Its normal cost (total for 9 days) is $6000 and its crash cost is $10,000 (total for 7 days).
What is the crash cost per day?
a. $14000
b. $7000
c. $5000
d. $2000
e. $1000
Related Book For
Introduction to Operations Research
ISBN: 978-1259162985
10th edition
Authors: Frederick S. Hillier, Gerald J. Lieberman
Posted Date: