Given this network plan, complete the following activities: Complete the network diagram by conducting a forward and
Fantastic news! We've Found the answer you've been seeking!
Question:
Given this network plan, complete the following activities:
Complete the network diagram by conducting a forward and backward pass through the network. Compute the early/late start time, early/late finish time, and slack time for each activity.
Using any approach you wish (e.g., trial and error) develop a loading chart for the project resources: Carpenters (C) and Electricians (E). Assume only one Carpenter is available and two Electricians are available.