You have been asked to use the expected value model to assess the risk in developing a
Fantastic news! We've Found the answer you've been seeking!
Question:
You have been asked to use the expected value model to assess the risk in developing a new product. Each strategy requires a different sum of money to be invested and produces a different profit payoff as shown below. Assume the probabilities for each state are 30%, 50%, and 20% respectively.
a. Using the concept of expected value, what risk (i.e. strategy) should be taken?
b. If the project manager adopts a go-for-broke attitude, what strategy should be selected?
c. If the project manager is a pessimist and does not have the option of strategy S5, what risk would be taken?
d. Would your answer to part c change if strategy S5 were an option?
Strategy | Complete Failure | Partial Success | Total Success | |
S1 | <50K> | <30k> | 70k | |
S2 | <80k> | 20k | 40k | |
S3 | <70k> | 0 | 50k | |
S4 | <200k> | <50k> | 150k | |
S5 | 0 | 0 | 0 |
Related Book For
Organizational Behavior Science The Real World and You
ISBN: 978-1111825867
8th edition
Authors: Debra L. Nelson, James Campbell Quick
Posted Date: