43. You are given the activity information below and the activity-on-node precedence diagram for a project...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
43. You are given the activity information below and the activity-on-node precedence diagram for a project at your company. 16 points (-4/error) a) Determine the critical path and its duration. What is your initial estimate for project completion time? Show your work on the next page. b) Fill in the table on the next page to determine the earliest start (ES) time, the earliest finish (EF) time, the latest start (LS) time, the latest finish (LF) time, and the Slack for each project activity. Slack = LS -ES or LF-EF. Time (days) Start A B Activity A B C D E F G ► C D Continued on next page Immediate Predecessor(s) --- --- A A, B C, D D E, F E F G 6 9 3 5 9 8 7 Finish Note: This precedence diagram is posted as a separate pdf also. a) Fill in the table with each path and show your work by calculating the time for each path in the table to determine the critical (longest) path(s). Add/delete rows in the table as needed. Path b) Fill in the ES & EF times in the table below working from Start to Finish. Then, fill in the LS & LF times working backwards from Finish to Start. After determining the ES, EF, LS, & LF times, calculate the Slack time for each activity using both Slack = LS - ES and Slack = LF-EF. Note: Both calculations must give you the same answers. ES EF LS Activity A B C D E F Time G LF Slack 43. You are given the activity information below and the activity-on-node precedence diagram for a project at your company. 16 points (-4/error) a) Determine the critical path and its duration. What is your initial estimate for project completion time? Show your work on the next page. b) Fill in the table on the next page to determine the earliest start (ES) time, the earliest finish (EF) time, the latest start (LS) time, the latest finish (LF) time, and the Slack for each project activity. Slack = LS -ES or LF-EF. Time (days) Start A B Activity A B C D E F G ► C D Continued on next page Immediate Predecessor(s) --- --- A A, B C, D D E, F E F G 6 9 3 5 9 8 7 Finish Note: This precedence diagram is posted as a separate pdf also. a) Fill in the table with each path and show your work by calculating the time for each path in the table to determine the critical (longest) path(s). Add/delete rows in the table as needed. Path b) Fill in the ES & EF times in the table below working from Start to Finish. Then, fill in the LS & LF times working backwards from Finish to Start. After determining the ES, EF, LS, & LF times, calculate the Slack time for each activity using both Slack = LS - ES and Slack = LF-EF. Note: Both calculations must give you the same answers. ES EF LS Activity A B C D E F Time G LF Slack
Expert Answer:
Answer rating: 100% (QA)
CCCCCCCFFFFFFHHHHH 183 som Start TFD D 0 A 2 2 2 TF6 O 37 67 13 ... View the full answer
Related Book For
Introduction to Operations Research
ISBN: 978-1259162985
10th edition
Authors: Frederick S. Hillier, Gerald J. Lieberman
Posted Date:
Students also viewed these accounting questions
-
A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below. Activity times are in weeks. Activity Precedence Activities...
-
The following additional information is available for the Dr. Ivan and Irene Incisor family from Chapters 1-5. Ivan's grandfather died and left a portfolio of municipal bonds. In 2012, they pay Ivan...
-
You are given the following information about a project consisting of six activities: (a) Construct the project network for this project. (b) Find the earliest times, latest times, and slack for each...
-
1. You are required to compare the results of your printed reports and the results of reports of the MYOB assignment book in your MYOB assignment. If it is assumed that two results of the reports are...
-
What steps can be taken to make controlling costs easier? Can these steps also be used to control other project parameters, such as scope?
-
Energy Star is a joint program between the US Department of Energy and the Environmental Protection Agency. What are the requirements for various IT devices to be certified as being Energy Star...
-
Assuming that one of management's control objectives is to restrict access to securities, which of the following would not be appropriate to satisfy the objective? a. Establish physical barriers over...
-
On January 1, 2016, Beatie Co. borrowed $200,000 cash from Central Bank by issuing a five-year, 6 percent note. The principal and interest are to be paid by making annual payments in the amount of...
-
Alexandra's Boutique has the following transactions related to its top-selling Gucci purse for the month of October. Alexandra's Boutique uses a periodic inventory system. Date Transactions October 1...
-
For the base case in this section, as a percentage of sales, COGS = 70 percent, SGA = 14 percent, R&D = 2.8 percent. Depreciation, Interest expense are fixed as stated. Tax Rate is 21 percent. 1.a...
-
Escareno Corporation provided its contribution format income statement for June. The company manufactures and sells a single product. Sales (8,400 units) $ 764.400 variable expenses 445.200...
-
When is the sales value method preferable to the quantity method as a means of allocating joint costs? In many manufacturing processes, waste products and by-products are produced. What problems do...
-
Specify the important elements of a production report.
-
What are inter-process profits? How are such profits taken into account while valuing closing stock from the point of view of the balance sheet? Do you subscribe to the view that the output of one...
-
Distinguish between process costing and job costing. Why is cost accumulation easier under the process costing system than under the job costing system?
-
What advantages are gained by separating fixed expenses from variable expenses? It has been said that the statement fluctuating overheads are those which vary with output is an unjustifiable...
-
A dry cell battery has just been connected to a light bulb. Explain energy transfer and energy transformation in this process when the Temperature of the battery and lightbulb is increasing
-
Refrigerant R-12 at 30C, 0.75 MPa enters a steady flow device and exits at 30C, 100 kPa. Assume the process is isothermal and reversible. Find the change in availability of the refrigerant.
-
Consider the following problem. Maximize Z = 3x 1 + 7x 2 + 2x 3 , Subject to And x 1 0, x 2 0, x 3 0. You are given the fact that the basic variables in the optimal solution are x 1 and x 3 . (a)...
-
Now reconsider the expanded version of the Silicon Dynamics problem described in Probs.16.3-2 and 16.4-2. (a) Use ASPE to construct and solve the decision tree for this problem. (b) Perform...
-
The results from a simulation run are inherently random. This problem will demonstrate this fact and investigate the impact of the number of trials on this randomness. Consider the example involving...
-
If the 3-in.-diameter short rod is made from brittle material having an ultimate strength of \(\sigma_{\text {ult }}=60 \mathrm{ksi}\), for both tension and compression, determine if the shaft fails...
-
If the 3-in.-diameter shaft is made from cast iron having tensile and compressive ultimate strengths of \(\left(\sigma_{\mathrm{ult}} ight)_{t}=40 \mathrm{ksi}\), and \(\left(\sigma_{\mathrm{ult}}...
-
The shaft consists of a solid segment \(A B\) and a hollow segment \(B C\), which are rigidly joined by the coupling at \(B\). If the shaft is made from A-36 steel, determine the maximum torque \(T\)...
Study smarter with the SolutionInn App