A production cost center charged budgeted overheads to cost units using a machine hour rate based on
Fantastic news! We've Found the answer you've been seeking!
Question:
A production cost center charged budgeted overheads to cost units using a machine hour rate based on the following estimates:
Total machine hours 10,000
Total fixed production overhead $50,000
Answer these questions below if a total 11,500 machine hours were used in actual and the total fixed production overheads is $55,000.
1. Compute the budgeted fixed production overhead absorption rate.
2. Calculate the amount of over- or under-applied overhead for the period