Question:
A Project has a PV of $60,000 at the status date of 10 months and a BAC of $185,000 at the end of the project. The Project schedule is 19 months and at the status date AC is $115,000 and EV for the project of $48,000
The project sponsor wants to know what the ETCdur forecast is IN MONTHS if a new EAC$ is used for revised funding, assuming the project will continue the way it's currently going.