A project manager has determined the following information for a project to be completed: Activities Successors immediately
Fantastic news! We've Found the answer you've been seeking!
Question:
A project manager has determined the following information for a project to be completed:
Activities | Successors immediately | Duration (in days) |
---|---|---|
A | B | 2 |
B | C | 2 |
C | AND | 5 |
D | F | 2 |
AND | 3 | |
F | AND | 4 |
Complete the following table:
Activities | Duration (in days) | DH | FH | DT | FT | MT | ML |
---|---|---|---|---|---|---|---|
A | |||||||
B | |||||||
C | |||||||
D | |||||||
AND | |||||||
F |
where DH is the earliest start date; FH is the earliest finish date; DT is the latest start date; FT is the latest end date; MT is the total margin; and ML is the free margin of activities. ( 10 points )
Points are awarded for the approach.
Related Book For
Operations Management
ISBN: 978-0071091428
4th Canadian edition
Authors: William J Stevenson, Mehran Hojati
Posted Date: