A project manager wants to calculate the probability of completing his project in 32 days. If the
Fantastic news! We've Found the answer you've been seeking!
Question:
A project manager wants to calculate the probability of completing his project in 32 days. If the variance of the critical path is 1.33 and the critical path is completed in 30 days, what is the probability of completing the project in 30 days?
a. 41.8% |
b. 95.82% |
c. 4.18% |
d. 0 |
e. 45.82% |