During planning. The team has identified the items in the following table as work to be done
Fantastic news! We've Found the answer you've been seeking!
Question:
- During planning. The team has identified the items in the following table as work to be done on the project. Draw a network diagram to graphically depict this flow. All relationships are F-S relationships, and duration is in days.
| Duration | Predecessor |
A | 1 | Start |
B | 2 | A |
C | 4 | B |
D | 2 | B |
E | 3 | B |
F | 4 | D |
G | 6 | F |
H | 1 | E |
I | 5 | H |
J | 2 | C |
K | 1 | G,I,J |
If task F change from F-S relationship to S-S relationship with Task D. What is the critical path?
If task F change from F-S relationship to F-F relationship with Task D. What is the critical duration?
What is the Critical Path?