Estimates Predecessors A 2 days None B 5 days A C 1 day B D 2 days
Fantastic news! We've Found the answer you've been seeking!
Question:
Estimates Predecessors
A 2 days None
B 5 days A
C 1 day B
D 2 days A
E 3 days B & D
F 12 days E & C
Draw a network diagram.
Identify the critical path, earliest start and finish and slack for each task.
Using MS Excel, produce a Gantt chart for this project.
What would happen if a new estimate for task D increases its expected duration from two days to six days? Would the project take longer? Would anything else change?