PROVIDE: Executive Summary- the bottom line up front; what you learned about the resolution to the problem.
Fantastic news! We've Found the answer you've been seeking!
Question:
PROVIDE:
- Executive Summary - the bottom line up front; what you learned about the resolution to the problem.
Introduction/Assumptions - Presentation - this is the process you employed to solve the problem
- Outcomes (tables, graphs, visuals) - provides support and most likely be part of the presentation section; additional tables can be placed in an appendix
- Conclusions - (make sure you answer all the question(s))
- Include a network diagram and table showing activity times use, event early start, early finish, late start, late finish and event slack.
- Determine the critical path
- Project duration ... is it completed in the desired 40 weeks?
- Determine the probability that the project can be completed in the desired 40 weeks.
- How much should the expected project completion time be shortened to achieve a goal of an 80 percent chance of completion in 40 weeks?
Related Book For
International Marketing And Export Management
ISBN: 9781292016924
8th Edition
Authors: Gerald Albaum , Alexander Josiassen , Edwin Duerr
Posted Date: