A local project being analyzed by PERT has 32 activities, 8 of which are on the critical
Fantastic news! We've Found the answer you've been seeking!
Question:
A local project being analyzed by PERT has 32 activities, 8 of which are on the critical path. If the estimated time along the critical path is 55 days with a project variance of 25, the probability that the project will be completed in 60 days or less is:
Select one:
Related Book For
Operations and Supply Chain Management
ISBN: 978-0078024023
14th edition
Authors: F. Robert Jacobs, Richard Chase
Posted Date: