A local project being analyzed by PERT has 25 activities, 9 of which are on the critical
Fantastic news! We've Found the answer you've been seeking!
Question:
A local project being analyzed by PERT has 25 activities, 9 of which are on the critical path. If the estimated time along the critical path is 46 days with a project variance of 36, the probability that the project will be completed in 40 days or less is: