Question 1) On the tab labeled CPM Network , you will find a skeleton AON network....
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Question 1) On the tab labeled CPM Network , you will find a skeleton AON network. The layout includes the activities required to complete the project. Based on the list of activities and predecessors on the CPM Calculation tab, enter the arcs (lines) to connect the activities. In the model you will note I left a single arc (line) for you. You may copy/paste this as many times as required to assemble your model. You can adjust the slope and length of the line as required by clicking your mouse on the line itself. Do not change any other formatting in the CPM Network tab, just enter the arcs. In the network model I have provided on the CPM Network tab, what do the lines you entered represent? Question 2) On the tab labeled CPM Calculation you will find a matrix where I have listed the activities for the project, the Predecessors, and the Days Required (duration) for each task as required. What is the definition of a predecessor? Question 3) On the tab labeled CPM Calculation you will find a matrix where I have started the computation to find the critical path for the project by calculating the early start/finish as part of the Forward Pass process. Make the entries in the spreadsheet on the CPM Calculation sheet to complete the Forward Pass. What is the earliest time the project can be completed (# of days)? Please note the spreadsheet is not set up with formulas for calculations; you must manually complete these calculations and enter the appropriate values in the spreadsheet. Question 4) After you have completed the Forward Pass, work backwards to complete the Backward Pass process. Make the entries in the spreadsheet on the CPM Calculation sheet to complete the Backward Pass. Please note the spreadsheet is not set up with formulas for calculations; you must manually complete these calculations and enter the appropriate values in the spreadsheet Question 5) After completing Questions 3 and 4, go back to the CPM Calculation tab and complete the Slack column. In the Critical Path column, put a Y in the cells that correspond to the activities that are on the critical path. In your response to this question here on this page, state the activities that are on the critical path and how you made the determination of the activities on the critical path. A 0 4 4 B C E D F 4 G 2 H 2 LEGEND: ES Early Start Time EF Early Finish Time LS Late Start Time LF Late Finish Time Duration Time or f Activity 1 2 J 1 A B C E D F G B H Activity AB с D E F G H I J Description Design Ordr/Rec Materials Construct Frame Prepare Engine Prepare Avionics Cover Frame Install Engine Paint Install Avionics Test Predecessors None A B B B C E, F F D, G, H I Days Req d 4 5 8 6 5 4 2 2 2 1 Forward Pass EST EFT 0 4 Backwards Pass LST LFT Slack Critical Path? Question 1) On the tab labeled CPM Network , you will find a skeleton AON network. The layout includes the activities required to complete the project. Based on the list of activities and predecessors on the CPM Calculation tab, enter the arcs (lines) to connect the activities. In the model you will note I left a single arc (line) for you. You may copy/paste this as many times as required to assemble your model. You can adjust the slope and length of the line as required by clicking your mouse on the line itself. Do not change any other formatting in the CPM Network tab, just enter the arcs. In the network model I have provided on the CPM Network tab, what do the lines you entered represent? Question 2) On the tab labeled CPM Calculation you will find a matrix where I have listed the activities for the project, the Predecessors, and the Days Required (duration) for each task as required. What is the definition of a predecessor? Question 3) On the tab labeled CPM Calculation you will find a matrix where I have started the computation to find the critical path for the project by calculating the early start/finish as part of the Forward Pass process. Make the entries in the spreadsheet on the CPM Calculation sheet to complete the Forward Pass. What is the earliest time the project can be completed (# of days)? Please note the spreadsheet is not set up with formulas for calculations; you must manually complete these calculations and enter the appropriate values in the spreadsheet. Question 4) After you have completed the Forward Pass, work backwards to complete the Backward Pass process. Make the entries in the spreadsheet on the CPM Calculation sheet to complete the Backward Pass. Please note the spreadsheet is not set up with formulas for calculations; you must manually complete these calculations and enter the appropriate values in the spreadsheet Question 5) After completing Questions 3 and 4, go back to the CPM Calculation tab and complete the Slack column. In the Critical Path column, put a Y in the cells that correspond to the activities that are on the critical path. In your response to this question here on this page, state the activities that are on the critical path and how you made the determination of the activities on the critical path. A 0 4 4 B C E D F 4 G 2 H 2 LEGEND: ES Early Start Time EF Early Finish Time LS Late Start Time LF Late Finish Time Duration Time or f Activity 1 2 J 1 A B C E D F G B H Activity AB с D E F G H I J Description Design Ordr/Rec Materials Construct Frame Prepare Engine Prepare Avionics Cover Frame Install Engine Paint Install Avionics Test Predecessors None A B B B C E, F F D, G, H I Days Req d 4 5 8 6 5 4 2 2 2 1 Forward Pass EST EFT 0 4 Backwards Pass LST LFT Slack Critical Path?
Expert Answer:
Related Book For
Financial and Managerial Accounting the basis for business decisions
ISBN: 978-0078025778
17th edition
Authors: Jan Williams, Susan Haka, Mark Bettner, Joseph Carcello
Posted Date:
Students also viewed these accounting questions
-
Beta of firm and idiosyncratic risk [10 points] The stock price of Beavers, a logging firm, tends to increase by 50% on average when the economy is booming. When the economy is weak, it goes down by...
-
The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks. The construction company must pay a penalty if the project is not...
-
Which of the following is NOT a source of capital for start-up businesses? a. Personal Savings b. Family and Friends c. Sales revenue O d. Bank Loans
-
Find r(t) and v(t) given a(t) and the initial velocity and position. a(t) = (t, 4), v(0) = (3,-2), r(0) = (0,0)
-
A random sample of size 100 is taken from a population with mean 1 and variance 0.04. Find the probability that the sample mean is between 0.99 and 1.
-
The following expenditures (in thousands) relating to plant assets were made by Lee Jung Ltd. during the first 2 months of 2025. 1. Paid 5,000 of accrued taxes at time plant site was acquired. 2....
-
Explain what the expected frequencies represent in a goodness-of-fit test.
-
Avery Corporations northwestern factory provided the following information for the last calendar year: Beginning inventory: Direct materials ...... $50,800 Work in process ...... 58,500 Ending...
-
You own a technology service provider business, named TechFeast Sdn. Bhd. Recently, your team consisting yourself, as the system analyst, a programmer, a database administrator and a project manager...
-
The Springfield School Board has made the decision to close one of its middle schools (sixth, seventh, and eighth grades) at the end of this school year and reassign all of next year's middle school...
-
The final answer has to be ordered exactly like the output and the residual row must be present. 5.7 LAB: Regression with nonlinear relationships Load the mtcars.csv data set into a data frame....
-
Problem Statement A local high school wants to keep track of statistics for the basketball team. The coach wants to get insight into average scores, low/high scores, etc. The coach would like to be...
-
During the 2008 credit crisis, the Federal Reserve implemented a policy of extensively purchasing mortgage-backed securities. Why did the Fed implement this policy and what could this policy...
-
580,000 Total stockholders' equity Stockholders' Equity (December 31) Common stock-$4 par value, 100,000 shares authorized, 41,400 shares issued, 3,000 shares in treasury Paid-in capital in excess of...
-
Will relationship selling continue to be part of the future of hospitality and tourism strategies? If so, how? If not, why? Discuss the 7 Steps of Selling (Prospecting & Qualifying; PreApproach;...
-
Required Information [The following Information applies to the questions displayed below] In each of the cases below, assume Division X has a product that can be sold to outside customers or to...
-
PURPOSE The purpose of this assignment is to develop learners' ability to identify and analyze the causes of low job satisfaction from an organisational behavior perspective and suggest how managers...
-
Describe a job you have had in the past or a job you are very familiar with. Indicate the negative aspects of the job and how it could be improved with current human resource management techniques.
-
Exhibit 259 identifies balanced scorecard performance measures. Review this exhibit and identify two measures from the customer perspective category that in the short run might be in conflict with...
-
An analysis of the income statement and the balance sheet accounts of Marys Fashions at December 31, 2015, provides the following information: Income statement items: Gain on Sales of Marketable...
-
Explain why it is necessary to distinguish between cash bud get estimates and operating budget estimates.
-
Preparing adjusting and subsequent journal entries Natsu Co. records prepaid expenses in balance sheet accounts. Natsus annual accounting period ends on October 31, 2008. The following information...
-
Preparing adjusting entries, adjusted trial balance, and financial statements Following is the unadjusted trial balance for Augustus Institute as of December 31, 2008, which initially records prepaid...
-
Preparing financial statements from the adjusted trial balance The adjusted trial balance for Speedy Courier as of December 31, 2008, follows. Required Use the information in the adjusted trial...
Study smarter with the SolutionInn App