Start A B 3 K L M N O P D 11 Activity J E F...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Start A B 3 K L M N O P D 11 Activity J E F 6 H Question 2.3 Consider the network described in the table below. (a) Which is the CP? (b) Calculate the duration of the CP. (c) Calculate the amount of slack time at activity H. (d) If activity I were delayed by ten time-units, what would be the impact on the project duration? Immediate Predecessor(s) -- J J J K, M K, M L, N 6 Pessimistic 15 9 10 3 9 10 10 K End Probable 10 8 6 3 5 7 8 Optimistic 8 7 5 3 1 4 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path. (c) Calculate the probability that the project will be completed in more than 28 time units. Question 2.4 The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time? Activity A B C D E F G H Normal Duration (hours) 2 3 5 3 6 1 7 10 Normal Cost ($) 10 15 25 20 30 5 35 50 Crash Duration Crash (hours) 2 2 4 1 4 1 6 7 Cost (S) 0 23 30 24 45 0 50 62 Immediate Predecessors None A B C C C,E F D,G Question 2.1 Walmart Canada debuted a new checkout system called "fast lane" that lets customers avoid cashiers and registers. Here's how it works: My Walmart users scan items with their phones as they shop. Once a user is finished shopping, they click "checkout" to receive a barcode. Next, the customer scans the order barcode at one of four scanning stations in the fast lane. This action charges the credit card the My Walmart user has on file. Finally, just before exiting the store, customers present their mobile receipts to a worker tending the fast lane. The system has debuted in a newly opened store in Toronto that Walmart says will serve as a prototype for future store renovations. Assume the new fast lane setup will replace 2 old cashier lanes that were staffed by a cashier and bagger on each lane. One worker mans all 4 scanning stations (answering questions, checking for un-scanned items, taking coupons, etc). Checkout on the new lanes takes 2 minutes (customers bag their own orders) while checkout with the old lanes took only 45 seconds. In addition, the electricity costs for both setups are $0.05 per checkout while bagging (material) costs are $0.10 per checkout with the old system and $0.15 for the new system. The new lanes also require $100/shift in capital costs. Assume that the lanes are always in use for 8 hours per day (1 shift) and that a worker makes $10/hour. (a) How many checkouts did the old system provide in a shift? (b) How many checkouts does the new system provide? (c) What is the multifactor productivity for each system? Question 2.2 Below is a network diagram that represents a university revamp project. The project manager analyzes this project using the critical path (CP) method. Activity durations are indicated on the network. Start A B 3 K L M N O P D 11 Activity J E F 6 H Question 2.3 Consider the network described in the table below. (a) Which is the CP? (b) Calculate the duration of the CP. (c) Calculate the amount of slack time at activity H. (d) If activity I were delayed by ten time-units, what would be the impact on the project duration? Immediate Predecessor(s) -- J J J K, M K, M L, N 6 Pessimistic 15 9 10 3 9 10 10 K End Probable 10 8 6 3 5 7 8 Optimistic 8 7 5 3 1 4 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path. (c) Calculate the probability that the project will be completed in more than 28 time units. Question 2.4 The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time? Activity A B C D E F G H Normal Duration (hours) 2 3 5 3 6 1 7 10 Normal Cost ($) 10 15 25 20 30 5 35 50 Crash Duration Crash (hours) 2 2 4 1 4 1 6 7 Cost (S) 0 23 30 24 45 0 50 62 Immediate Predecessors None A B C C C,E F D,G Question 2.1 Walmart Canada debuted a new checkout system called "fast lane" that lets customers avoid cashiers and registers. Here's how it works: My Walmart users scan items with their phones as they shop. Once a user is finished shopping, they click "checkout" to receive a barcode. Next, the customer scans the order barcode at one of four scanning stations in the fast lane. This action charges the credit card the My Walmart user has on file. Finally, just before exiting the store, customers present their mobile receipts to a worker tending the fast lane. The system has debuted in a newly opened store in Toronto that Walmart says will serve as a prototype for future store renovations. Assume the new fast lane setup will replace 2 old cashier lanes that were staffed by a cashier and bagger on each lane. One worker mans all 4 scanning stations (answering questions, checking for un-scanned items, taking coupons, etc). Checkout on the new lanes takes 2 minutes (customers bag their own orders) while checkout with the old lanes took only 45 seconds. In addition, the electricity costs for both setups are $0.05 per checkout while bagging (material) costs are $0.10 per checkout with the old system and $0.15 for the new system. The new lanes also require $100/shift in capital costs. Assume that the lanes are always in use for 8 hours per day (1 shift) and that a worker makes $10/hour. (a) How many checkouts did the old system provide in a shift? (b) How many checkouts does the new system provide? (c) What is the multifactor productivity for each system? Question 2.2 Below is a network diagram that represents a university revamp project. The project manager analyzes this project using the critical path (CP) method. Activity durations are indicated on the network.
Expert Answer:
Related Book For
Operations Management Sustainability And Supply Chain Management
ISBN: 9780137476442
14th Edition
Authors: Jay Heizer, Barry Render, Chuck Munson
Posted Date:
Students also viewed these general management questions
-
Can I get a list of accounts or sections that belongs under a balance sheet and a income statement?
-
Planned Order Receipt Planned Order Release Gross Requirements for D-239 Ending Inventory Net requirements Planned Order Receipt Planned Order Release Gross Requirements for E-239 Ending Inventory...
-
The production of paper involves a pulping step to break down wood chips into cellulose and lignin. In the Kraft process, an aqueous, pulping-feed solution, known as white liquor, is used that...
-
Given that Hometown Care, Inc.'s stock is currently selling for $40 a share, calculate the amount of money that Calvin Haskins will make (or lose) on each of the following transactions. Assume that...
-
The Product based "P" for the implementation of your marketing. Services are the "Product" that is intangible and what does the Pricing -P stands and the Pricing Methods in the Four Ps.
-
The velocity components of an incompressible, two-dimensional velocity field are given by the equations \[ \begin{aligned} u & =y^{2}-x(1+x) \\ v & =y(2 x+1) \end{aligned} \] Show that the flow is...
-
Wins Companies, a home improvement store chain, reported the following summarized figures: Requirements 1. Compute Wins Companies current ratio at May 31, 2012 and 2011. 2. Did Wins Companies current...
-
A soft tennis ball is dropped onto a hard floor from a height of 1.95 m and rebounds to a height of 1.56 m. (Assume that the positive direction is upward.) (a)Calculate its velocity (in m/s) just...
-
Complete Tsate's Form 1040-SR, Schedules A, B and D, Form 8949, Form 6252 and Qualified Dividends and Capital Gain Tax Worksheet. Tsate Kongia (birthdate 02/14/1954) is an unmarried high school...
-
Create the Relational Model for the Flubber database based on your ER Diagram, meeting all the same requirements. This should be syntactically correct to test in a MySQL database. 1. Create an...
-
The following two figures represent the labor market for two industries that require workers with the same skills and experience; however, Industry B is characterized by much noisier working...
-
Use the cereals data set for Exercises 712. Report the standard error of each imputation. Compare the standard errors for the imputations obtained in Exercises 9 and 11. Explain what you find....
-
Find the eigenvalues, eigenvectors, AM, and GM of each eigenvalue and decide whether the matrix is defective or not. Then, transform the matrix into either a diagonal or a Jordan matrix, whichever is...
-
Find the eigenvalues, eigenvectors, AM, and GM of each eigenvalue and decide whether the matrix is defective or not. Then, transform the matrix into either a diagonal or a Jordan matrix, whichever is...
-
An engine operates on the air standard diesel cycle. The conditions at the start of the compression stroke are \(353 \mathrm{~K}\) and \(100 \mathrm{kPa}\), while at the end of compression stroke the...
-
If the ratio between the magnetic flux densities at the point (x, y) near a straight wire 2 carrying an electric current is BY distances of these two point from the wire is so the ratio between the...
-
Perform the operation by first converting the numerator and denominator to scientific notation. Write the answer in scientific notation. 7,200,00/0.000009
-
Consider the data for a simple project at Carlos Lopezs real estate development company, as given in the following table. a) Note that this project has only one path. What is the expected completion...
-
Green Forever (Problem $5.12) has decided to add an automatic string feeder system with cost and revenue estimates as shown below to the GF Deluxe model. a) What is the new revenue retrieval value...
-
Premier Bicycle Company, located in Knoxville, Tennessee, knows that the strength of its extensive supply chain is a key factor in its production success. The 90-year-old company is the nations...
-
What are the key differences between financing entrepreneurial and established companies?
-
What is the purpose of staged financing?
-
What can and can't we learn from successful start-ups like Pandora's Box and Spotify?
Study smarter with the SolutionInn App