Sundi is assigned to a project team. Her functional manager is Jay, but her project leader is
Fantastic news! We've Found the answer you've been seeking!
Question:
Sundi is assigned to a project team. Her functional manager is Jay, but her project leader is Eli. Her company has a weak matrix structure. Who is most likely responsible for her performance review?
Neither Jay nor Eli is responsible, since the project sponsor will conduct the review.
Jay is responsible for the review.
Jay and Eli will share the responsibility.
Eli is responsible for the review.