The Advanced Tech Company has a project to design an integrated information data base for a...
Fantastic news! We've Found the answer you've been seeking!
Question:
![image text in transcribed](https://s3.amazonaws.com/si.experts.images/answers/2024/05/664781b9e39e3_297664781b9c1e62.jpg)
![image text in transcribed](https://s3.amazonaws.com/si.experts.images/answers/2024/05/664781ba36e9d_298664781ba242de.jpg)
![image text in transcribed](https://s3.amazonaws.com/si.experts.images/answers/2024/05/664781ba8c382_298664781ba6e3e1.jpg)
![image text in transcribed](https://s3.amazonaws.com/si.experts.images/answers/2024/05/664781bb05a45_298664781badc1f5.jpg)
Transcribed Image Text:
The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project are given in the following table. Indirect project costs amount to $250 per day. The company will incur a $100 per day penalty for each day the project lasts beyond day 20. a. What is the project's duration if only normal times are used? Normal Time Crash Time Crash Cost Activity Normal Cost ($) (days) (days) ($) Immediate Predecessor(s) A 6 800 3 2,000 B 5 1,000 3 1,200 C 5 500 3 1,500 A, B D 3 1,200 2 1,500 B E 5 1,500 2 2,100 C, D F 3 1,300 1 1,400 E G 4 900 3 1,000 E H 5 500 5 500 G The project duration is day(s). (Enter your response as an integer.) b. What is the minimum-cost schedule? With the minimum-cost schedule, the project duration is day(s) (Enter your response as an integer.) c. What is the critical path for the minimum-cost schedule? The critical path for the minimum-cost schedule is Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project (shown below to the right). In addition, you have asked your team to estimate the amount of time that they would expect each of the activities to take. Their responses are shown in the following table: Time Estimates (days) Activity Optimistic Most Likely Pessimistic A 5 7 10 B 3 9 11 Start Finish C 5 7 8 D 2 3 6 B E E 3 8 10 a. What is the expected completion time of the project? The expected completion time is days. (Enter your response as an integer.) Q a. What is the expected completion time of the project? The expected completion time is days. (Enter your response as an integer.) b. What is the probability of completing the project in 20 days? Refer to the standard normal table. The probability of completing the project in 20 days is (Enter your response rounded to four decimal places.) c. What is the probability of completing the project in 16 days? The probability of completing the project in 16 days is (Enter your response rounded to four decimal places.) The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project are given in the following table. Indirect project costs amount to $250 per day. The company will incur a $100 per day penalty for each day the project lasts beyond day 20. a. What is the project's duration if only normal times are used? Normal Time Crash Time Crash Cost Activity Normal Cost ($) (days) (days) ($) Immediate Predecessor(s) A 6 800 3 2,000 B 5 1,000 3 1,200 C 5 500 3 1,500 A, B D 3 1,200 2 1,500 B E 5 1,500 2 2,100 C, D F 3 1,300 1 1,400 E G 4 900 3 1,000 E H 5 500 5 500 G The project duration is day(s). (Enter your response as an integer.) b. What is the minimum-cost schedule? With the minimum-cost schedule, the project duration is day(s) (Enter your response as an integer.) c. What is the critical path for the minimum-cost schedule? The critical path for the minimum-cost schedule is Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project (shown below to the right). In addition, you have asked your team to estimate the amount of time that they would expect each of the activities to take. Their responses are shown in the following table: Time Estimates (days) Activity Optimistic Most Likely Pessimistic A 5 7 10 B 3 9 11 Start Finish C 5 7 8 D 2 3 6 B E E 3 8 10 a. What is the expected completion time of the project? The expected completion time is days. (Enter your response as an integer.) Q a. What is the expected completion time of the project? The expected completion time is days. (Enter your response as an integer.) b. What is the probability of completing the project in 20 days? Refer to the standard normal table. The probability of completing the project in 20 days is (Enter your response rounded to four decimal places.) c. What is the probability of completing the project in 16 days? The probability of completing the project in 16 days is (Enter your response rounded to four decimal places.)
Expert Answer:
Related Book For
Operations Management Processes and Supply Chains
ISBN: 978-0132807395
10th edition
Authors: Lee J. Krajewski, Larry P. Ritzman, Manoj K. Malhotra
Posted Date:
Students also viewed these general management questions
-
Uneven Cash Flow Stream Find the present values of the following cash flow streams. The appropriate interest rate is 12%. ( Hint: It is fairly easy to work this problem dealing with the individual...
-
Classify the two given samples as independent or dependent. Sample 1: The weights of 43 oranges grown in Californianothing Sample 2: The weights of 37 oranges grown in Floridanothing Question content...
-
The Advanced Tech Company has a project to design an integrated information database for a major bank. Data for the project are given in Table. Indirect project costs amount to $300 per day. The...
-
Lungameni Enterprises (Pty) Ltd ("Lungameni Enterprises") manufactures product A, which it sells to local customers at a mark-up of 25%. Lungameni Enterprises currently absorbs its overhead costs on...
-
Indicate whether a CPA may provide each of the following services, and whether independence is required, by placing a check in the appropriatebox. May Provide; Independence May Provide; Independence...
-
Write a code segment to perform a sequential search on a one-dimensional array. Assume that the set of data could contain duplicates. If the item being searched for is found in the array, record the...
-
\((-13)+(-102)\) Complete the indicated calculation.
-
The comparative statements of Beulah Company are presented below. Additional data:The common stock recently sold at $19.50 per share.InstructionsCompute the following ratios for 2013.(a) Current. (b)...
-
. Current Attempt in Progress On January 1, 2022, Sunland Inc. entered into an agreement to lease 20 computers from Drummond Electronics. The terms of the lease agreement require three annual...
-
why is it important to reweigh the capsules after filling them
-
Our survey indicates that in the past three months, employees' ability to self-identify personal strengths and weaknesses has improved 12 percent. [2] Initial Data Analysis indicates that the ability...
-
4. Write a program in java to implement the single source shortest Path Algorithm(Dijktra's Algorithm ). S A ( 3 B D 2 1 E
-
Discuss the works of the following on scholars in political sociology Antonio Gramsci Max weber Robert Michelle
-
3. Melania K. is in possession of a check signed and issued by Donald T. that says, "Pay to the order of Melania K. $5,000" and a note signed and issued by Donald T. that says, "I promise to pay to...
-
es Thermal Rising, Incorporated, makes paragliders for sale through specialty sporting goods stores. The company has a standard paraglider model, but also makes custom-designed paragliders....
-
Traditional finance theory states that "the higher the risk the higher the return it should generate" (Hillier et al., 2018). However, the current regulatory regime is aimed at reducing systemic risk...
-
From the choice of simple moving average, exponential smoothing, and linear regression analysis, which forecasting technique would you consider the most accurate? Why? please write it in word...
-
\(\frac{14}{27} \div \frac{7}{12}\) Perform the indicated operations. Reduce to lowest terms.
-
\(\frac{44}{75} \div \frac{484}{285}\) Perform the indicated operations. Reduce to lowest terms.
-
\(\left(\frac{1}{5} \div\left(\frac{3}{10}+\frac{11}{15} ight) ight) \times\left(\frac{2}{21}+\frac{5}{9} ight)-\left(\frac{8}{15} \div \frac{4}{33} ight)^{2}\) Perform the indicated operations....
![Mobile App Logo](https://dsd5zvtm8ll6.cloudfront.net/includes/images/mobile/finalLogo.png)
Study smarter with the SolutionInn App