The Aggie Watch Corporation manufactures watches on a conveyor belt with 6 stations. One worker stands at
Fantastic news! We've Found the answer you've been seeking!
Question:
The Aggie Watch Corporation manufactures watches on a conveyor belt with
stations. One worker stands at each station and performs the following tasks:
a Where in the process is the bottleneck?
b What is the capacity, in watches per hour, of the assembly line ignore the time it
takes for the first watch to come off the line?
c What is the direct labor content for the processes on this conveyor belt?
d What is the utilization of the worker in station B ignore the time it takes for the
first watch to come off the line
e How many minutes of idle time will the worker in station C have in hour
ignore the time it takes for the first watch to come off the line