The critical path calculation shows B-D-E-F-H is the critical path, and the expected project completion time...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
The critical path calculation shows B-D-E-F-H is the critical path, and the expected project completion time is 21 weeks. After viewing this information, management requested overtime be used to complete the project in 16 weeks. Thus, crashing of the project is necessary. The following information is relevant. Time (weeks) Cost ($) Activity s.t. A B D E F G H Normal 3 6 2 5 4 3 9 3 Crash 1 3 1 3 3 1 4 2 Normal Crash 900 2,000 4,100 500 1,800 1,500 3,000 8,000 1,700 1,000 1,000 2,400 1,850 3,900 9,800 2,000 (a) Formulate a linear programming model that can be used to make the crashing decisions for this project. (The objective function should be the additional cost of crashing. Let x; additional cost of crashing. Let x; = the finish time for activity i and y; = the amount of time activity iis crashed where i = A, B, C, D, E, F, G, and H.) Min 400y + 700 +500y +300yd+350y + 450y+360yg +1000yh X constraint A constraint B C depends on A D depends on C D depends on B E depends on D F depends on E G depends on C G depends on B H depends on G H depends on F finish time for H xa3- xa+yz 6 xc+yc-x 2 C a x_+y g X xd+yd-yc5 xd+yd-xb5 xe+ye-xq4 ty tng xe X x + y g xh+yn Vg - x 9 h16 e 3 xz 9 -x>3 g Xh+Vhxf 3 X X X X X maximum crashing for A maximum crashing for B maximum crashing for C maximum crashing for D maximum crashing for E maximum crashing for F maximum crashing for G maximum crashing for H ya 2 6 3 1 Yd2 Ye 1 Yf2 Vg 5 h 1 x X X X X X (b) Solve the linear programming model and make the minimum cost crashing decisions. What is the amount of crash time (in weeks) for each activity? Activity A B D E F G H Crash Time | | What is the added cost (in dollars) of meeting the 16-week completion time? $ Norton Industries is installing a new computer system. The activities, the activity times, and the project network are as follows. Activity Time A B D F F G H Start 3 6 2 5 4 3 9 3 A B D G E F H Finish The critical path calculation shows B-D-E-F-H is the critical path, and the expected project completion time is 21 weeks. After viewing this information, management requested overtime be used to complete the project in 16 weeks. Thus, crashing of the project is necessary. The following information is relevant. Time (weeks) Cost ($) Activity s.t. A B D E F G H Normal 3 6 2 5 4 3 9 3 Crash 1 3 1 3 3 1 4 2 Normal Crash 900 2,000 4,100 500 1,800 1,500 3,000 8,000 1,700 1,000 1,000 2,400 1,850 3,900 9,800 2,000 (a) Formulate a linear programming model that can be used to make the crashing decisions for this project. (The objective function should be the additional cost of crashing. Let x; additional cost of crashing. Let x; = the finish time for activity i and y; = the amount of time activity iis crashed where i = A, B, C, D, E, F, G, and H.) Min 400y + 700 +500y +300yd+350y + 450y+360yg +1000yh X constraint A constraint B C depends on A D depends on C D depends on B E depends on D F depends on E G depends on C G depends on B H depends on G H depends on F finish time for H xa3- xa+yz 6 xc+yc-x 2 C a x_+y g X xd+yd-yc5 xd+yd-xb5 xe+ye-xq4 ty tng xe X x + y g xh+yn Vg - x 9 h16 e 3 xz 9 -x>3 g Xh+Vhxf 3 X X X X X maximum crashing for A maximum crashing for B maximum crashing for C maximum crashing for D maximum crashing for E maximum crashing for F maximum crashing for G maximum crashing for H ya 2 6 3 1 Yd2 Ye 1 Yf2 Vg 5 h 1 x X X X X X (b) Solve the linear programming model and make the minimum cost crashing decisions. What is the amount of crash time (in weeks) for each activity? Activity A B D E F G H Crash Time | | What is the added cost (in dollars) of meeting the 16-week completion time? $ Norton Industries is installing a new computer system. The activities, the activity times, and the project network are as follows. Activity Time A B D F F G H Start 3 6 2 5 4 3 9 3 A B D G E F H Finish
Expert Answer:
Related Book For
Quantitative Methods for Business
ISBN: 978-0324651751
11th Edition
Authors: David Anderson, Dennis Sweeney, Thomas Williams, Jeffrey cam
Posted Date:
Students also viewed these general management questions
-
Norton Industries is installing a new computer system. The activities, the activity times, and the project network are as follows: The critical path calculation shows B-D-E-F-H is the critical path,...
-
A curve has equation y = x 2 ln 3x. Find the value of dy/dx and d 2 y/dx2 at the point where x = 2.
-
A partial bond amortization schedule for Chiasson Corp. is provided below. Chiasson has a December 31 year end. (a) Was the bond issued at a premium or discount? (b) Record the interest payment on...
-
A nuclear fission power plant produces about 1.50 GW of electrical power. Assume that the plant has an overall efficiency of 35.0% and that each fission event produces 200. MeV of energy. Calculate...
-
A uniform bar of length \(l\) and mass \(m\) is hinged at one end \((x=0)\), supported by a spring at \(x=\frac{2 l}{3}\), and acted upon by a force at \(x=l\), as shown in Fig. 13.32. Derive the...
-
Averys All-Natural Company supplies wigs and hair care products to beauty salons throughout Texas and the Southwest. The accounts receivable clerk for Averys All- Natural prepared the following...
-
What struck you about the Growth Mindset video? How does it relate to yourself and what you've been thinking about your success in this course? Think about someone youknow who speaks well. What is it...
-
After preparing a draft statement of profit or loss for the year ended 30 September 20X5 and adding the current year's draft profit (before any adjustments required by notes (i) to (iii) below) to...
-
1- Connect the circuit shown in Fig. 3. Use the NPN transistor BC107 V. +12V Re 470k www VB R BC107 Ve Figure 3: Practical Fixed Bias Transistor Circuit Transistor 1.(BC107) Quantity VB Vc VBEQ IBQ...
-
The following table contains some data showing the effect of molar concentration of a solution on the absorbance (optical density) reading from a spectrophotometer. Concentration (M) 0.13 0.28 0.43...
-
Consider the one-line diagram shown below, which depicts an industrial distribution system consisting of a 3-phase system operating at a voltage of Vs = 410 V. The impedance of the distribution lines...
-
Descriptions of Variables Variable Description Sports 1 = athletes, 2 = non-athletes Gender 1 = males, 2 = females Anger-Out (AO) high scores demonstrate that people deal with anger by expressing it...
-
Consider the single variable function defined by y = 4x - x. a. Find a parameterization of the form r(t) = (x(t), y(t)) that traces the curve y = 4x 4xx on the interval from x = -3 to x = 3. - b....
-
Notes on similarities, differences, and patterns you see across all companies, your ideas on potential explanations for these, and your recommendation on the best company to invest in. What are the...
-
Using thermodynamic data from Appendix 4, calculate G at 258C for the process: 2SO 2 (g) + O 2 (g) 88n 2SO 3 (g) where all gases are at 1.00 atm pressure. Also calculate DG8 at 258C for this same...
-
Newton Manufacturing produces scientific calculators. The models are N350, N450, and the N900. Newton has planned its distribution of these products around eight customer zones: Brazil, China,...
-
The purpose of this exercise is to provide practice using the LINGO or Excel solvers. Find the values of X and Y that minimize the function Min X2 - 4X + Y2 + 8Y + 20 Do not assume nonnegativity of...
-
Assume that a third grocery store, Quick Stop Groceries, enters the market share and customer loyalty situation described in Section 17.1. Quick Stop Groceries is smaller than either Murphys...
-
A healthy diet is becoming increasingly important for consumers, especially women aged 2535. As a result, they are taking active steps to ensure they are eating healthy but are also looking for other...
-
Lael was just hired by Best East Motels into their manager training program and was excited about the potential benefits after her graduation from Florida State University. Working part-time and...
-
Sophie just completed a sales training course with one of the firms most productive sales representatives, Emma. At the end of the first week, Sophie and Emma sat in a motel room filling out their...
Study smarter with the SolutionInn App