The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME
Fantastic news! We've Found the answer you've been seeking!
Question:
The following activities are part of a project to be scheduled using CPM:
ACTIVITY | IMMEDIATE PREDECESSOR | TIME (WEEKS) |
A | — | 8 |
B | A | 5 |
C | A | 9 |
D | C | 6 |
E | B
D | 4 |
F | D | 7 |
G | E
F | 4 |
What is the critical path?
How many weeks will it take to complete the project?
How much slack does activity B have?