The following table gives the time lines of costs and benefits for two different projects. Project A
Fantastic news! We've Found the answer you've been seeking!
Question:
- The following table gives the time lines of costs and benefits for two different projects.
Project A | Project B |
Time period | Benefits | Costs | Benefits | Costs |
0 | 225 | 0 | 0 | 300 |
1 | 200 | 0 | 200 | 0 |
2 | 150 | 0 | 150 | 0 |
3 | 0 | 400 | 150 | 0 |
a. Suppose that the rate of interest is 3%. Which one is the most preferred according the the standard CBA rule? Show all your calculations.
b. Repeat the analysis of part (a) for a rate of interest equal to 1%.
c. Provide an economic explanation for any similarities or differences you find in the preferred outcomes in parts (a) and (b).