The gross requirements for Item X are specified for the beginning of weeks 1 through 8 in
Question:
The gross requirements for Item X are specified for the beginning of weeks 1 through 8 in the table that follows. The product structure for the item is given in the figure: The lead time of each item is specified within square brackets. For example, the lead time for Item X is 1 week. The number of units required for each lower level part is specified within parentheses. For example, each unit of Item B requires 1 unit of Part C and 2 units of Part D.
There are no units in inventory and no scheduled receipts. Complete the MRP calculations to determine the planned order releases for Item H. (Note that Item H occurs twice on the product structure. Note also that you will need to complete the calculations for other items on the Product Structure.)