The Walthaus Corporation standard cost sheet is as follows: Direct material 4 feet at $5.00 per foot
Question:
The Walthaus Corporation standard cost sheet is as follows:
Direct material 4 feet at $5.00 per foot
Direct labor 3 hours at $10.00 per hour
Variable overhead 3 hours at $2.00 per hour
Fixed costs 3 hours at $1.00 per hour
Additional Information:
Actual Results:
Purchased 30,000 lbs. of material at $5.25 per pound (there were no beginning or ending inventories of materials);
The direct labor cost incurred was 26,000 hours at $9.75 per hour;
Actual variable overhead incurred, $50,000;
Actual fixed overhead costs incurred $43,000.
Overhead is applied to work in process on a direct labor-hours basis.
The company produced 8,000 units of product during the period.
The number of hours estimated for the calculation of the rate of application of fixed general expenses amounted to 45,000 hours.
What are the variations in price and material efficiency?
Horngrens Financial and Managerial Accounting
ISBN: 978-0133866292
5th edition
Authors: Tracie L. Nobles, Brenda L. Mattison, Ella Mae Matsumura