There are 200 units in inventory at the start of week 1. What are the net requirements
Fantastic news! We've Found the answer you've been seeking!
Question:
There are 200 units in inventory at the start of week 1. What are the net requirements in week 4 if there is a scheduled receipt of 100 units every other week and a two week production lead time?
Gross Requirements | Week 1 550 | Week 2 450 | Week 3 400 | Week 4 400 | Week 5 500 |
Scheduled receipts | 100 | 0 | 100 | 0 | 100 |
Projected ending Inventory | |||||
Net Requirements | |||||
Planned Receipts | 350 | 450 | |||
Planned Orders | 350 | 300 |
Group of answer choices
- 250
- 300
- 400