Livernonions Industries uses a kanban system to manage production of the BR-549 subassembly. In an eight-hour day,
Fantastic news! We've Found the answer you've been seeking!
Question:
Livernonions Industries uses a kanban system to manage production of the BR-549 subassembly. In an eight-hour day, they use 1200 units and use containers that can hold 50 units each. It takes 120 minutes to fill and move a container of parts to the right place on the BR-549 line that is currently rated at a 25% safety factor. How many production hours of inventory are needed?
Group of answer choices
- 375
- 2.4
- 2.5
- 7.5