Task | Length in weeks | Immediate predecessors | CRASH COST PER WEEK | MAXIMUM WEEKS CRASHED |
A | 7 | - | 200 | 1 |
B | 12 | - | 250 | 3 |
C | 7 | A | 250 | 1 |
D | 6 | A | 300 | 1 |
E | 1 | B | 0 | |
F | 1 | C.D | 0 | |
G | 3 | D E | 200 | 1 |
H | 3 | F | 350 | 1 |
I | 2 | G | 0 |