Your project has four activities. Below is the current status of each activity. Activity A was supposed
Question:
Your project has four activities. Below is the current status of each activity.
Activity A was supposed to cost $350,000 when complete. Its costs so far are $265,000. It is 45% complete. The activity has completed 7 weeks of a planned 15-week schedule.
Activity B is at the end of week 2 of a planned 4-week effort. It is 75% complete. It was to cost $190,000 when finished. Its costs to date are $150,000.
Activity C is finished. It finished 2 weeks late. It cost $200,000 and it was planned to cost $250,000.
Activity D is at the end of its fourth of a planned 6-week schedule. It has cost $350,000 so far. It was estimated to cost $500,000 when finished. It is approximately 55% complete.
Using these data, calculate the following.
1.Calculate the CV, SV, CPI, and SPI for each activity and the total project.
2.What is your assessment of the project at this time?