Mary is planning her wedding and develops the following preliminary information. a. Draw the network for this

Question:

Mary is planning her wedding and develops the following preliminary information.image text in transcribed

a. Draw the network for this project.

b. Identify the critical path(s)?

c. What is the project completion time?

d. Construct an early start date Gantt chart.

e. As a project manager, where would you focus your attention given your analysis?

Step by Step Answer:

Related Book For  answer-question
Question Posted: