You are in charge of the advertising program for the Boston Red Sox baseball team during their spring training season in Fort Myers, Florida. You have defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season or you may not have this job next year—the pressure is on!image text in transcribed

a. Draw the project network.

b. What is the earliest completion time for this advertising project?

c. What activity has the largest amount of slack?
How many weeks is it?

d. If activity D is delayed two weeks, what is the revised earliest completion time?

e. If activity C in the original problem is crashed from four to two weeks, what is the revised critical path and project completion time?