On a 1000-MVA common base, a two-area system interconnected by a tie line has the following parameters:

Question:

On a 1000-MVA common base, a two-area system interconnected by a tie line has the following parameters:

image text in transcribed

The two areas are operating in parallel at the nominal frequency of \(60 \mathrm{~Hz}\). The areas are initially operating in steady state with each area supplying \(1000 \mathrm{MW}\) when a sudden load change of \(187.5 \mathrm{MW}\) occurs in area 1. Compute the new steady-state frequency and change in tie-line power flow (a) without LFC, and (b) with LFC.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Power System Analysis And Design

ISBN: 9781111425777

5th Edition

Authors: J Duncan Glover, Mulukutla S Sarma, Thomas Overbye

Question Posted: