Build a Gantt chart by using Microsoft Project based on the list of tasks as shown in

Question:

Build a Gantt chart by using Microsoft Project based on the list of tasks as shown in Figure C-16. This mini-project is to build part of the user interface for a new system. The following Gantt charts show without and with critical path highlighted.

Task Name Duration Start Finish Resource Names Prede Mar 4, 12 Mar 11, 12 WTFSS MTWTFSSMTWTFSS MTWTESSM Mar 18, '12 Mar 25 - Total Project 14 days Thu 3/1/12 Tue 3/20/12 Brye, Tammy Bryee,Tammy 2 Meet with users 2 days Thu 3/1/12 Fri 3/2/12 Вrycе, Tammy Thu 3/1/12 Wed 3/7/12

a. How many days does this project take? Can you shorten it any? (One easy way to view the total project length is to make a single highest-level task, with all other tasks demoted beneath it.)

b. Does it contain resource conflicts? 

c. What does leveling do to the length of the project?

d. Can you make other reassignments of work between Bryce and Tammy that will shorten the project?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Systems Analysis and Design in a Changing World

ISBN: 978-1305117204

7th edition

Authors: John W. Satzinger, Robert B. Jackson, Stephen D. Burd

Question Posted: