The following data resulted from a study taken on a horizontal milling machine: Pieces produced per cycle:
Question:
Pieces produced per cycle: 8.
Average measured cycle time: 8.36 minutes.
Average measured effort time per cycle: 4.62 minutes.
Average rapid traverse time: 0.08 minutes.
Average cutting time power feed: 3.66 minutes.
Performance rating: 115 percent.
Allowance (machine time): 10 percent.
Allowance (manual time): 15 percent.
The operator works on the job a full eight-hour day and produces 380 pieces. How many standard hours does the operator earn? What is her efficiency for the eight-hour day?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Niebels Methods, Standards and Work Design
ISBN: 978-0073376318
13th edition
Authors: Andris Freivalds, Benjamin Niebel
Question Posted: