The Miller Company uses skilled and unskilled labor to do a particular construction project. The cost of

Question:

The Miller Company uses skilled and unskilled labor to do a particular construction project. The cost of doing the project depends on the number of hours of skilled labor and the number of hours of unskilled labor used, the relationship being
C = 4 − 3X1 − 4X2 + 2X21 + 3X22 + X1X2
where C is cost (in thousands of dollars), X1 is the number of hours (in thousands) of skilled labor, and X2 is the number of hours (in thousands) of unskilled labor.
a. Find the number of hours of skilled labor and the number of hours of unskilled labor that will minimize the cost of doing the project.
b. If the Miller Company has to purchase a license costing $2,000 to do this project (and if the cost of this license is not included in C), will this alter the answer to part (a)? If so, how will the answer change?
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Managerial Economics Theory Applications and Cases

ISBN: 978-0393912777

8th edition

Authors: Bruce Allen, Keith Weigelt, Neil A. Doherty, Edwin Mansfield

Question Posted: