Wave Wake Marine Company has total estimated factory overhead for the year of $1,200,000, divided into four

Question:

Wave Wake Marine Company has total estimated factory overhead for the year of $1,200,000, divided into four activities: fabrication, $450,000; assembly, $210,000; setup, $240,000; and inspection, $300,000. Wave Wake manufactures two types of boats: a speedboat and a bass boat. The activity-base usage quantities for each product by each activity are as follows:
Wave Wake Marine Company has total estimated factory overhead for

Each product is budgeted for 200 units of production for the year. Determine
(a) The activity rates for each activity and
(b) The factory overhead cost per unit for each product, using activity-based costing.