In preparing to launch a new product, a marketing manager has determined the critical path for her

Question:

In preparing to launch a new product, a marketing manager has determined the critical path for her department. The activities and the mean and variance of the completion time for each activity along the critical path are shown in the accompanying table. Determine the mean and variance of the completion time of theproject.