Activity A is worth ($100,) is complete, and actually cost ($150. Activity) B is worth ($500,) is
Question:
Activity A is worth \($100,\) is complete, and actually cost \($150.
Activity\) B is worth \($500,\) is 75% complete, and has actually cost \($400\) so far. Activity C is worth \($500,\) is 25% complete, and has actually cost \($200\) so far. What is the estimated cost to completion for the project?