Calculate the direct cost of labor for a project team member using the following data: Hourly rate:

Question:

Calculate the direct cost of labor for a project team member using the following data: Hourly rate: $35/hr. Hours needed: 150 Overhead rate: 55%

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer: