J. Smith (Project Manager for Print Software Pty Ltd) wants you to prepare a project network. Calculate

Question:

J. Smith (Project Manager for Print Software Pty Ltd) wants you to prepare a project network. Calculate the early, late and slack activity times. Determine the planned project duration and identify the critical path. His assistant has collected the following information for the Colour Printer Driver's Software Project:

IDDescriptionPredecessorTime
AExternal specificationsNone8
BReview design featuresA2
CDocument new featuresA3
DWrite softwareA60
EProgram and testB60
FEdit and publish notesC2
GReview manualD2
HAlpha siteE, F20
IPrint manualG10
JBeta siteH, I10
KManufactureJ12
LRelease and shipK3
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Project Management In Practice

ISBN: 9781743767320

2nd Edition

Authors: Neil Pearson, Erik W. Larson, Clifford F. Gray

Question Posted: