The planning department of an electronics firm has set up activities for the development and production of

Question:

The planning department of an electronics firm has set up activities for the development and production of a new MP3 player. Given the information below, develop a project network.

IDActivity descriptionActivity predecessorActivity time (weeks)
1StaffNone2
2Develop market program13
3Select channels of distribution18
4Patent112
5Pilot production14
6Test market54
7Ad promotion24
8Set up for production4,616

The project team has requested that you create a network for the project, and determine whether the project can be completed in 45 weeks.