The planning department of an electronics firm has set up activities for the development and production of
Question:
The planning department of an electronics firm has set up activities for the development and production of a new MP3 player. Given the information below, develop a project network.
ID | Activity description | Activity predecessor | Activity time (weeks) |
---|---|---|---|
1 | Staff | None | 2 |
2 | Develop market program | 1 | 3 |
3 | Select channels of distribution | 1 | 8 |
4 | Patent | 1 | 12 |
5 | Pilot production | 1 | 4 |
6 | Test market | 5 | 4 |
7 | Ad promotion | 2 | 4 |
8 | Set up for production | 4,6 | 16 |
The project team has requested that you create a network for the project, and determine whether the project can be completed in 45 weeks.