Suppose you evaluated the best-case, most likely, and worst-case duration estimates for an activity and determined that

Question:

Suppose you evaluated the best-case, most likely, and worst-case duration estimates for an activity and determined that they were 3 days, 4 days, and 8 days, respectively.
Using PERT estimation techniques, what would be the expected duration for the activity?

a. 4 days

b. 8 days

c. 5 days

d. 4.5 days

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question
Question Posted: