Suppose you evaluated the best-case, most likely, and worst-case duration estimates for an activity and determined that
Question:
Suppose you evaluated the best-case, most likely, and worst-case duration estimates for an activity and determined that they were 3 days, 4 days, and 8 days, respectively.
Using PERT estimation techniques, what would be the expected duration for the activity?
a. 4 days
b. 8 days
c. 5 days
d. 4.5 days
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management Achieving Competitive Advantage
ISBN: 9781292269146
5th Global Edition
Authors: Jeffrey K.Pinto
Question Posted: