The construction team is behind schedule on its project. The customer is considering giving the project to

Question:

The construction team is behind schedule on its project. The customer is considering giving the project to another company if the project cannot be put back on track. The team is considering putting more resources on the critical path to accelerate the schedule. This is an example of what?

a. Staff acquisition

b. Crashing

c. Re-planning

d. Fast-tracking