The sponsor of a project to move the loan processing system from C++ to the intranet is
Question:
The sponsor of a project to move the loan processing system from C++ to the intranet is deciding whether the project should continue or be scrapped. The project has been plagued with issues. So far, \($1M\) has been spent on the project. Of the following, what best describes the \($1M\) that has been spent so far?
a. Opportunity cost
b. Budgeted cost of work performed
c. Sunk cost
d. Phase 1 cost