The optical disk project team has started gathering information that is necessary for developing the project network

Question:

The optical disk project team has started gathering information that is necessary for developing the project network (predecessor activities and activity times, in weeks). The results of their meeting are found in the following table.

ActivityDescriptionDurationPredecessor
1Define scope6None
2Define customer problems31
3Define data records and relationships51
4Mass storage requirements52,3
5Consultant needs analysis102,3
6Prepare installation network34,5
7Estimate costs and budget24,5
8Design section 'point' system14,5
9Write request proposal54,5
10Compile vendor list34,5
11Prepare mgmt. control system56,7
12Prepare comparison report59,10
13Compare system 'philosophies'38,12
14Compare total installation28,12
15Compare cost of support38,12
16Compare customer satisfaction level108,12
17Assign philosophies points113
18Assign installation cost114
19Assign support cost115
20Assign customer satisfaction points116
21Select best system1$11,17,18,19,20$
22Order system121




The project team has requested that you create a network for the project and determine if the project can be completed in 45 weeks.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Project Management In Practice

ISBN: 9781743767320

2nd Edition

Authors: Neil Pearson, Erik W. Larson, Clifford F. Gray

Question Posted: