The project administrator is preparing a preliminary budget for a project and adds in the cost of

Question:

The project administrator is preparing a preliminary budget for a project and adds in the cost of a new computer for the project team to use. What type of cost would this computer purchase represent?

a. Variable

b. Direct

c. Indirect

d. Variable direct

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question
Question Posted: