The project manager for a large project being developed in northern Ontario recognizes that it will be

Question:

The project manager for a large project being developed in northern Ontario recognizes that it will be necessary for her to maintain a close presence at the construction site during its development, and has negotiated the use of a building for her team near the construction project. The cost of the building must be factored into the project cost and will increase with use; that is, the cost of heating and other utilities is subject to change depending upon weather and team use. What type of cost would this building represent?

a. Variable direct

b. Indirect

c. Nonrecurring

d. None of the above

Fantastic news! We've Found the answer you've been seeking!